I‑Sete judgment: ECJ increases protection for tenderers – German Procurement Acceleration Act comes under pressure from EU law
At a glance
In its I-Sete judgment, the ECJ reinforces the effective protection afforded to tenderers under primary law and declares that the automatic removal of the suspensive effect of a first-instance public procurement review procedure, without hearing the tenderers and without the court carrying out its own balancing of interests, is contrary to EU law.
The decision raises further questions regarding the compliance with EU law of this year’s German Public Procurement Acceleration Act, specifically concerning the removal of the suspensive effect of an immediate appeal in the event of a negative decision by the Public Procurement Tribunal.
Contracting authorities and tenderers should now carefully review their procurement and appeal strategies in order to rule out risks of damages and to secure effective protection under primary law.
.The German Procurement Acceleration Act (Vergabebeschleunigungsgesetz), which came into force on 1 July 2026 (see also our series of news items, most recently Noerr Insight of 24 April 2026), has sharply reduced primary legal protection in public procurement. The reform is now also coming under scrutiny under EU law: in its judgment of 17 September 2026 in Joined Cases C‑266/25 and C‑267/25 (“I‑Sete”), the Court of Justice of the European Union (“ECJ”) set limits under EU law on the lifting of the suspensive effect of remedies in public procurement proceedings. Following this judgment, a national court may not be required to lift the suspensive effect of a remedy without first hearing the unsuccessful tenderer and without being able to specifically weigh up all the interests at stake.
The judgment concerns a Portuguese rule. Whether the principles it sets out also apply to the new section 173(1) of the German Competition Act is still unclear. Despite this, the judgment makes it appropriate to examine the German reform more closely in the light of EU law. We therefore start by outlining the latest developments in primary legal protection in public procurement (see A.), before explaining the underlying case and the ECJ’s key reasoning (see B.). We then consider the possible implications for German public procurement practice (see C.) and conclude with an outlook (see D.).
A. Recent developments in primary legal protection in public procurement under German law
The Federal Armed Forces Procurement Acceleration Act (Bundeswehrbeschaffungsbeschleunigungsgesetz – see also our series of news items, most recently Noerr Insight of 10 February 2026), which entered into force on 14 February 2026, removed the suspensive effect of immediate appeals (sofortige Beschwerden) to a decision by a public procurement tribunal rejecting an application for review for certain types of procurement covered by the Act (former section 16(1) of the Federal Armed Forces Procurement Acceleration Act).
The German Procurement Acceleration Act, which entered into force on 1 July 2026, extended this approach to all types of public procurement. Under the new section 173(1) of the German Competition Act (Gesetz gegen Wettbewerbsbeschränkungen), an immediate appeal has no suspensive effect if the public procurement tribunal has rejected the application for review. At the same time, where the contracting authority succeeds before the public procurement tribunal, the prohibition on awarding the contract – which takes effect when the tribunal informs the authority that an application for review is pending – generally ends as soon as the tribunal’s decision is announced (revised section 169(1), second sentence of the German Competition Act).
This means that the contracting authority may award the contract even though an immediate appeal by the unsuccessful tenderer may still be brought before a higher regional court or is already pending there. Once the contract has been validly awarded, it can generally no longer be set aside in review proceedings (section 168(2), first sentence of the German Competition Act). The unsuccessful tenderer is then generally confined to secondary legal protection. This is usually limited to compensation for reliance loss, mainly involving reimbursement of the costs of preparing the tender or taking part in the procedure, and requires the tenderer to have had a genuine chance of being awarded the contract if the infringement of procurement rules had not taken place (see section 181 of the German Competition Act). In practice, the possibility of claiming compensation for loss of profit by way of secondary legal protection available in certain cases is subject to significant hurdles. In particular, the tenderer must establish and prove that it would have been awarded the contract had the procurement procedure been conducted properly. Against this background and given that references gained through the performance of public contracts cannot be compensated for by damages in the form of money, primary legal protection in public procurement is very important.
Under the law in force until 30 June 2026, an immediate appeal initially had suspensive effect. This effect generally ended two weeks after the expiry of the two-week appeal period. If the public procurement tribunal had rejected the application for review, the procurement divisions of the higher regional courts could accept an application to extend the suspensive effect until the appeal had been decided (previous section 173(1) of the German Competition Act).
The new provisions are highly controversial under constitutional law. The procurement division of Dusseldorf Higher Regional Court (OLG Düsseldorf) has referred to the Federal Constitutional Court (Bundesverfassungsericht) the question of whether the former section 16(1) of the Federal Armed Forces Procurement Acceleration Act is compatible with the guarantee of legal protection under Article 19(4) of the German Constitution, or Basic Law (Grundgesetz), and the general right to access to justice (Article 20(3) of the Constitution) (order of 18 May 2026 – VII‑Verg 6/26; see also our Noerr Insight of 26 May 2026). In view of the identical regulatory content of the revised section 173(1) of the German Competition Act, the same question also arises in relation to the Procurement Acceleration Act. Section 16(1) of the Federal Armed Forces Procurement Acceleration Act became redundant as a special provision as a result of the revised section 173(1) of the German Competition Act and was therefore repealed by the Procurement Acceleration Act.
The ECJ’s I‑Sete judgment now brings another challenge, this time from EU law.
B. EU requirements for tenderer protection in light of the I‑Sete judgment
I. Underlying case
The case before the ECJ concerned two procurement procedures conducted by EDIA, a Portuguese state-owned infrastructure company. They involved construction contracts awarded by EDIA to two competitors of I‑Sete for floating photovoltaic power plants at pumping stations. The unsuccessful tenderer, I‑Sete, challenged the award decisions before the Administrative and Tax Court of Porto, the court of first instance, seeking to ensure that the automatic suspensive effect of its remedy would prevent the contracts from being awarded. EDIA argued that any delay in performing the contracts could result in the loss of EU funding and that the tenderer’s remedy should therefore have no suspensive effect.
Portuguese law provided for a special procedure in such cases. After a ten-day period had expired, the contracting authority could apply for the automatic suspensive effect to be provisionally lifted. The court could initially decide on that application within 48 hours and without first hearing the tenderer. The conditions for lifting the suspensive effect were, in the ECJ’s view, easy to satisfy; the risk of losing funding was for example presumed in certain circumstances. If the court lifted the suspensive effect, the authority would be entitled to enter into the contract with the successful tenderer despite the ongoing court proceedings, and the contract could then no longer be set aside by a court.
The referring court asked the ECJ whether this rule was compatible with Directive 89/665/EEC on review procedures for the public sector (“Remedies Directive”) and with the right to an effective remedy under Article 47 of the Charter of Fundamental Rights of the European Union (“Charter”).
II. ECJ’s reasoning
The ECJ emphasised the importance of interim relief in public procurement proceedings. Under Article 2(3) of the Remedies Directive, the contracting authority as a rule may not enter into the contract before the review body has decided on the application for interim measures or on the application for review. Article 2(5) of the Remedies Directive allows the consequences of interim measures to be considered in the light of all interests likely to be harmed and the public interest.
Lifting the suspensive effect impairs the practical effectiveness of the remedy and thus interferes with the right to an effective remedy protected by Article 47 of the Charter – a right which, given its legislative purpose, the Remedies Directive is specifically intended to secure. Any such restriction must above all be provided for by law in accordance with Article 52(1) of the Charter and must respect the essence of that right.
In the ECJ’s view, the Portuguese rule failed to meet the above requirement. It made it so easy to lift the suspensive effect and constrained the court so extensively that the default position, being suspensive effect, was effectively turned on its head. Although the decision formally remained in the court’s hands, the rule meant that the need to weigh up interests under EU law had in practice already been carried out abstractly by the legislature and with final effect. In support of this conclusion, the ECJ specifically noted that in practice it was impossible for the claimant tenderer to prove that the suspensive effect should be maintained.
The court pointed out that the risk of a loss of EU funding could be taken into account when weighing up interests. However, it added that this risk alone must not result in the contracting authority’s interests effectively always prevailing and that what matters is that the competent court specifically weighs up the public and private interests at stake in the proceedings concerned, for which an inter partes procedure is a basic prerequisite.
As a result, the ECJ held that Article 2(3) to (5) of the Remedies Directive read in the light of Article 47 of the Charter excludes any rule requiring a court to lift suspensive effect without first hearing the tenderer concerned and without being able to carry out an assessment of all the interests at stake.
C. Implications of the judgment for German public procurement practice
The I‑Sete judgment convincingly underscores the central importance of the right to an effective remedy and a fair hearing in the context of primary legal protection in public procurement. It expressly and rightly emphasises that the rule at issue in the proceedings disregards the intention behind the Remedies Directive, which is to enable an effective review of a contract award or planned award by preventing contracting authorities from making a contested planned award irreversible by implementing it.
I. Does the I‑Sete judgment also apply to section 173(1) of the German Competition Act?
The I‑Sete judgment does not, however, directly answer the question whether the revised section 173(1) of the German Competition Act is contrary to EU law.
At first glance, section 173(1) of the Act goes even further than the Portuguese rule: the procurement divisions of the higher regional courts now have no procedural means of giving an immediate appeal suspensive effect after the public procurement tribunal has issued a decision rejecting the application for review. In the Portuguese case, by contrast, it was still formally up to the court to decide whether the suspensive effect would remain in place or be lifted, even though the decision had already been determined in practice by the Portuguese rule, which was contrary to EU law.
There is, however, a very relevant difference between the two situations. In Portugal, the issue was the lifting of the automatic suspensive effect in proceedings before the first-instance review body. In contrast, the German provision concerns the second-instance remedy of an immediate appeal after the public procurement tribunal has rejected the application for review at first instance; during the first-instance proceedings, the prohibition on awarding the contract under section 169(1), first sentence of the German Competition Act was in force.
This difference is essential for the legal assessment. The right to an effective remedy under Article 47 of the Charter generally guarantees effective legal protection by a court within the meaning of Article 267 TFEU, but not by multiple courts (ECJ, judgment of 17 July 2014 – C‑169/14, para. 36). It therefore does not give rise to a right to appeal through multiple levels of jurisdiction. Given this, the I‑Sete judgment cannot automatically be understood as requiring the Remedies Directive to provide for a suspensive effect of an application for review at every level of jurisdiction and in every situation.
It should nevertheless be noted that, according to the prevailing and correct view in legal literature, where the national law of the Member States grants remedies and thus provides for multiple levels of jurisdiction (as in Germany with the immediate appeal), the requirements of Article 47 of the Charter also apply at those levels. Although Article 47 does not in itself require all remedies to have suspensive effect, such effect is indispensable where necessary to ensure the remedy’s effectiveness and where implementation would otherwise be irreversible. This is the case in public procurement, since a contract that has been validly awarded can generally no longer be set aside. In this respect, the right to an effective remedy therefore guarantees at the very least the procurement division’s power to order that the immediate appeal have suspensive effect, or even that such effect applies automatically as a general rule.
However, in its judgment of 18 January 2024, Case No C‑303/22 (“Cross”), the ECJ took a different view, holding that even where national law provides for multiple levels of jurisdiction, suspensive effect need only apply at first instance – even where that body is not a court.
It is not possible to determine conclusively whether the Cross judgment can be applied to the present situation: even in that case, the I‑Sete judgment may be understood as a nuanced recalibration of an interpretation that construes the requirements of Article 47 of the Charter too narrowly, significantly strengthening effective primary legal protection in the light of the right to an effective remedy.
Such a right cannot, however, be derived directly from the Remedies Directive itself. The Directive requires that an independent body review a contract award decision at first instance; that body need not necessarily be a court within the meaning of Article 267 TFEU. It also requires that during this period the contracting authority be unable to enter into the contract before the review body has decided on an application for interim measures or on the merits. The public procurement tribunal may still order interim measures in review proceedings and weigh up interests when considering whether to authorise the award of the contract in advance (section 169(2) of the German Competition Act).
Moreover, according to the ECJ’s case law, the public procurement tribunal is a “court” within the meaning of Article 267 TFEU and therefore for the purposes of the Remedies Directive (ECJ, judgment of 18 September 2014 – C‑549/13, para. 23), even though the tribunals are not classified as courts under national law.
II. Interpretation in line with EU law, obligation to refrain from applying national rules and refer cases?
Courts must interpret national law as far as possible in conformity with EU law. If a conflict with EU law cannot be avoided by means of interpretation, the primacy of EU law means that the conflicting national rule must not be applied in the proceedings in question. If the procurement divisions consider the new section 173(1) of the German Competition Act to be contrary to EU law, they must refrain from applying it. One question that remains open, however, is what procedural mechanism could instead be used to order the immediate appeal to have suspensive effect or to prohibit the awarding of the contract.
Since the procurement divisions of Germany’s higher regional courts also decide cases at final instance, they may also be required under Article 267(3) TFEU to refer the question of whether the revised section 173(1) of the German Competition Act is compatible with EU law, provided that the question is relevant to the decision and the ECJ has neither already ruled on a materially similar case nor left no room for reasonable doubt as to the answer to the question referred.
III. Practical guidance for authorities and tenderers
Tenderers should object to any potential procurement law infringements at an early stage and provide detailed grounds for their applications for review. Following the reform, the proceedings before the public procurement tribunal have become even more significant in practice: if the application is rejected, the contracting authority may generally award the contract despite an immediate appeal.
Contracting authorities should not regard the possibility of awarding the contract immediately after an adverse decision by the public procurement tribunal as a risk-free option. They should instead carefully assess whether to proceed with the award. If an immediate appeal remains pending, the assessment of the revised section 173(1) of the German Competition Act under EU law – and under constitutional law – may be relevant in certain cases. It therefore remains advisable to carefully review the tribunal’s decision and the risks of awarding the contract, especially considering the potentially substantial damages claims that may be brought by tenderers who are successful at second instance.
D. Outlook
The I‑Sete judgment does not categorically reject the acceleration of public procurement procedures. Instead, it requires that the interests in accelerating proceedings must not automatically prevail over those of an unsuccessful tenderer, and that the tenderer’s right to an effective remedy must be preserved. Where there is a risk that suspensive effect will be lifted, the court has to weigh up the interests in the specific case and, as a general rule, give the tenderer concerned an opportunity to comment.
For German law, no court has yet ruled on whether the revised section 173(1) of the German Competition Act is contrary to EU law. The judgment nevertheless raises the unanswered question of whether removing the suspensive effect of an immediate appeal is compatible with the requirements for effective legal protection. As the I‑Sete judgment clearly demonstrates, this is not merely a question of constitutional law; it must also be resolved under EU law. The future of suspensive effect for immediate appeals in public procurement proceedings may therefore be decided not only by Germany’s Constitutional Court in Karlsruhe, but also by the ECJ in Luxembourg.